January 2008

bulltet_point links bullet_right

Members of the Board of Oban Bay Marine were involved in a number of meetings to progress Community Consultation, and input from stakeholders and other interested parties was sought. A community consultation meeting open to all with an interest in Oban Bay and the surrounding area chaired by Jim Mather MSP took places on Friday 18th January 2008 in the Argyllshire Gathering Halls

bulltet_point Community Consultation meeting   bullet_right

March 2008
Initial seabed survey work commenced.  

Oban's business community pledged support towards funding of planning for a proposed new pontoon and breakwater development for the inner harbour, including a Project Manager and various surveys.

The Board agreed to appoint Morag Brown as a consultant,  funding officer and Project Manager for this development. Morag had previously  been involved with a similar project for Tobermory Harbour.  

Spring 2008
The Board and Morag Brown undertook the preparation of a planning application to install pontoons in Oban Bay. 


June 2008

OBM lodge a planning application for the formation of multi-use, short stay / transit 60 berth marina for the heart of Oban Bay with Argyll and Bute Council
see below for extracts of photomontages and plans passed

 bulltet_point  planning application 2008 - Argyll and Bute Council website    bullet_right

back to top    back to archive homepage

click on any picture to see larger

photomontage of proposed pontoon development

photomontage of proposed pontoon development

photomontage of proposed pontoon development

 

copy of approved plan

copy of approved plan
large scale plan is 1.3MB
back to top    back to archive homepage

November 2008
All aspects in obtaining permission for the proposed Short Stay Pontoon Development within Oban Harbour were concluded: detailed planning consent from Argyll and Bute council  - dredging consent from FRS Marine Lab. In Aberdeen  - Marine navigation and safety from Marine Coastguard Agency (Scottish Ex.)

Oban Bay Marine's plans to provide a short stay pontoon development in Oban was the highest scoring individual project in Argyll and Bute's Project Board for regeneration funds for the 5 towns of Argyll and was allocated a grant of £900,000, while meetings with other funding sources continued.

Argyll and Bute Council CHORD programme and OBM 

Oban Bay Marine - 2010 - 2011

While the above show the plans with consent in place,  modifications continue to be considered - this sketch of what Oban Bay Marine is hoping to achieve - below - was prepared in 2010 ...


large scale image is 1.1MB